Fall 2005. There was a lot to do and a lot to learn about
how to do it. So construction is being done in multiple phases.
This spreads the work, the materials acquisition and expenses
out over an extended time. Besides, this is a hobby, not a job,
so go slow and enjoy it. I began construction of trestle. Phase
one work was largely delayed until spring due to early wintery
weather. We had snow and rain with below freezing temperatures
so the ground was hard to work.
In mid-winter I ran across an article on the Web about pond
siting. One statement in it said, "For all the work that goes
into building a pond, you should put it where you can see it from
the house most of the year". That made good sense. So I moved
pond on the plan and also the location of the towns. This was
a whole lot easier than digging a new pond and filling in the
old one. Planning is a good thing to do. This was almost like
starting over. I'm glad I did not get more construction done.
I volunteered to have my garden with an operating garden railroad
around a pond on the tour for the North American Lily Society
International Lily Show in July, 2006. A fixed deadline, July
15, for lots of projects.
Spring, 2006. Construction of the layout
itself was preceded by 2 related projects, replacing the concrete
in the driveway and building the pond. The old concrete from
the driveway was used to construct a retaining wall to hold dirt
excavated from the pond and build the stream bed that will feed
the pond. It was also used for the construction of 2 tunnels
for the train. Some dirt from digging the pond was used for fill in
the driveway. About 600 marigolds were raised from seed in my
green house and planted in the gardens and flowerbeds around the yard.
Summer, 2006. The pond was dug and lots of garden
and flower bed work was completed. Next some track was laid.
Many thanks to Margaret, my wife, and friend Lars for helping.
1 July, 2006 arrived quickly. Roadbed for the loop around the
pond (the Captown loop) was started. On 14 July 2006 the first
train was running. Only one problem was encountered - two pair
of wires ran from the power supply to the track as 2 loops were
planned but only one constructed at this time. I hooked up the
wrong pair to the first loop. A quick swap of the wires and
the train sprung to life. The tour was the next day. About 130
people visited. Most had never seen a garden railroad before.
On 9 August 2006 construction of the Alville loop began. The next
day trains were running over the Alville loop with a temporary
connection to the Captown loop.
Fall, 2006 was the construction of the Alville loop
extension around the pond. 28 Sept 2006 marked the beginning
of the roadbed preparation. On 10 Oct 2006 the grade crossing
installed. People and the lawn mower need to safely cross the
tracks. Someday signals will be installed here. Some snow fell
in October but progress continued. Track was laid and the
Alville extension was completed and operating. 24 Nov 2006 the
Alville station siding is in place. By the end of November the
Alville tunnels were completed except for portals.
Winter, 2006-2007. A wooden truss build bridge, the first
of at least 3 bridges was built. Some of the boys in my Royal
Ranger Outpost came to run trains and have a hot dog roast. To add
to the fun I built several prototype buildings out of cardboard.
These were industries so we could do some realistic switching.
Spring, 2007. Some landscape with plants around the
pond and on and around the hills through which the tunnels pass
was done. Also some finishing of areas of track that was laid
earlier was done.
Summer, 2007. This brought the lengthening of the Alville loop
along the west side and to the north. Construction of the
train shed has started.
Fall, 2007. Finished most of the trainshed and Alville loop north extension.
Winter, 2007-2008. Built a short a deck bridge. Started building a rotary
snowplow.
Spring, 2008. Installed bridge between the tunnels.
Summer, 2008. Extended the Alville loop north extension farther north.
Winter, 2008-2009. Built a prototype turntable of all wood. Final version will
be made of composite plastic-wood material to stand up to rain and snow.
Built 3 more tunnel portals.
Spring, 2009. Finally got the ridge cover on the train shed. Turntable was
installed as were the new tunnel portals. Plastic rail was installed in the
trainshed for storage tracks. Electrical panel for power control to the trainshed
tracks was installed. A real door replaced the 1x8 board that was being used.
Summer, 2009. Added a 2 track siding for the logging camp area and a track that runs
through the trainshed.
|